APICS Certified in Planning and Inventory Management(Part 2) Sample Questions:
1. Manufacturing flexibility can be measured by using:
A) scrap level.
B) changeover time.
C) cycle time,
D) labor productivity.
2. Which of the following observations in a manufacturing plant best illustrates the poka-yoke technique of process design?
A) An andon is installed.
B) Customized containers hold mixed sets of parts.
C) A part attribute defines correct orientation.
D) The number of types of fasteners is reduced from 25 to 5.
3. Locating service facilities differs from locating manufacturing or distribution facilities primarily because service locationdecisions are:
A) driven by revenue concerns, while manufacturing and distribution location decisions are driven by costs.
B) determined after surveying customers, while manufacturing and distribution location decisions are determined after surveying suppliers.
C) driven by real estate costs, while manufacturing and distribution location decisions are driven by productcosts.
D) driven by competition, while manufacturing and distribution location decisions are not.
4. Which of the following priority rules is most consistent with the objective of meeting due dates?
A) Fewest operations remaining
B) First-come-first-served
C) Shortest processing time (SPT)
D) Slack time per operation
5. Which of the following planning modules considers the longest-range planning goals?
A) Resource planning
B) Rough-cut capacity planning (RCCP)
C) Capacity requirements planning (CRP)
D) Input/output analysis
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: C | Question # 3 Answer: A | Question # 4 Answer: D | Question # 5 Answer: D |