CTTAM Civil-Engineering-Technology Exam Overview:
| Certification Vendor: | CTTAM |
| Exam Name: | Technical Examination - Civil Engineering Technology C.E.T |
| Exam Number: | Civil-Engineering-Technology |
| Exam Duration: | 180 minutes |
| Exam Format: | Multiple Choice, Written Response |
| Certificate Validity Period: | Valid for life (maintained through continuing education) |
| Available Languages: | English |
| Real Exam Qty: | 110-112 |
| Exam Price: | $350 CAD |
| Related Certifications: | Certified Technician (C.Tech.) |
| Passing Score: | 70% |
| Recommended Training: | CTTAM Exam Preparation Materials Technology Accreditation Canada |
| Exam Registration: | CTTAM Official Registration |
| Sample Questions: | CTTAM Civil-Engineering-Technology Sample Questions |
| Exam Way: | In-person or remote online proctored |
| Pre Condition: | Must hold C.Tech. certification, be a registrant in good standing, and have 1+ year of relevant work experience at technologist level |
| Official Syllabus URL: | https://cttam.com/competency-exams |
CTTAM Civil-Engineering-Technology Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Transportation Engineering | 15% | - Highway & Road Design
|
| Geotechnical Engineering | 18% | - Soil Mechanics & Foundation Engineering
|
| Civil Engineering Fundamentals | 25% | - Engineering Mathematics & Applied Science
|
| Structural Engineering | 20% | - Structural Analysis & Design
|
| Water Resources & Environmental Engineering | 12% | - Hydrology & Water Systems
|
| Construction Management & Materials | 10% | - Construction Methods & Project Management
|
CTTAM Technical Examination - Civil Engineering Technology C.E.T Sample Questions:
1. Which of the following tests would most likely be used to determine if engineered fill was placed to meet contract specifications?
A) Sieve analysis
B) Triaxial compression test
C) Moisture content check
D) Compaction test
2. What type of survey stake is shown in the image below?
A) A centreline stake
B) A grade stake
C) A benchmark stake
D) A slope stake
3. A concrete mix is onsite and at its specified slump of 80 mm. The pour requires a slump of 200 mm. The concrete onsite meets all other requirements. What action should be taken?
A) Add water to the concrete onsite
B) Order a different concrete mix
C) Add high-range water reducer to the concrete onsite
D) Add low-range water reducer to the concrete onsite
4. Which of the following situations would cause the most serious delay on a project?
A) A severe storm flooded a trench before it could be backfilled.
B) Several bones, ranging in size from 10 cm to 60 cm, were found during excavation operations.
C) A gas service line to a residence was hit, causing the line to rupture.
D) A worker suffered a broken arm on the work site.
5. A civil engineering technologist has been given the task of drawing a foundation plan for a building that measures 20 m × 30 m. The drawing will be produced on a C1 sized sheet, which measures 648 mm × 917 mm. Which of the following is the best scale for the plan?
A) 1:250
B) 1:25
C) 1:5
D) 1:50
Solutions:
| Question # 1 Answer: D | Question # 2 Answer: A | Question # 3 Answer: C | Question # 4 Answer: B | Question # 5 Answer: D |