Nokia PDM_2002001060 Exam Overview:
| Certification Vendor: | Nokia |
| Exam Name: | CPM - Certified Project Manager |
| Exam Number: | PDM_2002001060 |
| Available Languages: | English |
| Real Exam Qty: | 213-215 |
| Exam Duration: | 60 minutes |
| Related Certifications: | Nokia Project & Portfolio Management Certification |
| Passing Score: | Not officially published |
| Exam Format: | Multiple Choice, Scenario-based |
| Exam Price: | Not officially published |
| Certificate Validity Period: | Not officially published |
| Recommended Training: | Nokia Certified Project Manager Training |
| Exam Registration: | Nokia Training & Certification Portal |
| Sample Questions: | Nokia PDM_2002001060 Sample Questions |
| Exam Way: | Online proctored or authorized test center |
| Pre Condition: | Basic project management knowledge; no mandatory official prerequisites |
| Official Syllabus URL: | https://www.nokia.com/networks/training/ |
Nokia PDM_2002001060 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Project Execution & Monitoring | - Change control and issue resolution - Team management and communication - Cost adherence, earned value and KPI tracking |
| Project Closure & Handover | - Contract acceptance and site quality review - Financial closure and lessons learned |
| Nokia-Specific Processes & Tools | - IPM, PCA, PARD and P-SQI metrics - Vendor management and back-to-back principles |
| Project Initiation & Business Case | - Project charter and stakeholder identification - Business case definition and approval |
| Project Planning & Scope Management | - Risk, quality and procurement planning - Schedule, resource and cost planning - Scope definition and work breakdown structure |
Nokia CPM Sample Questions:
1. Which milestone(s) must always be completed before invoicing?
A) Provisional acceptance.
B) It depends on the contractual terms.
C) Final acceptance.
D) Internal acceptance.
2. Nokia orders the I&C from a subcontractor. The subcon, not completely familiar with this new equipment, requires a Nokia technician to complete the service. What is the correct way to proceed?
A) A new change request is created and approved by project manager, then the technician is provided to support the subcon; however an internal acceptance is not provided because of the incomplete service from the subcontractor.
B) The technician is immediately provided to properly support our subcontractor and quickly complete the service and enable customer acceptance and invoicing.
C) A new change request is created and approved by the project manager then the technician is provided to support the subcontractor; an outgoing claim to the subcontractor is applied just after the service is completed and then the internal acceptance is provided.
D) The technician will support the subcontractor only after the newly created change request is approved.
3. Which of the following is NOT part of the IPM suite?
A) Sales management.
B) Document management.
C) Change management.
D) Site data management.
4. Why is the project resource plan required during the 'Create Customer Solution' phase?
A) To initiate recruitment of the project team.
B) In order to make a services cost calculation.
C) To reserve resources from the resource manager, so no other project can use them.
D) To reserve subcontractor resources.
5. An accuracy KPI has dropped significantly compared to previous periods. After some initial checks it turns out that the data is correct. What is the right way to proceed?
A) Organize a meeting with NPO in order to make an action plan to improve.
B) Communicate the deviation to the project stakeholders.
C) Inform the CT head at the next CT meeting.
D) Organize a meeting with key team members in order to identify root causes and make an action plan to improve.
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: C | Question # 3 Answer: A | Question # 4 Answer: B | Question # 5 Answer: D |