API Pipeline Construction Inspector Sample Questions:
1. Define quality management system realization in terms to process
A) Part of quality management focussed on providing confidence that quality requirements will be fulfilled.(ISO 9000 3.3.6)
B) Process of establishing, documenting, implementing, maintaining and continually improving a quality management system.(ISO 9000 3.4.3)
C) A part of quality management Focused on the ability to fulfil quality requirements.The quality requirements can be related to any aspect such as effectiveness efficiency or traceability.
D) d) welding she will not be done we,re floors are combustible(ANDI Z49.1 6.1)
2. Red
A) Grading
B) Thermal
C) Mechanical
D) Electrical
3. Define Crossing Company
A) Is the singular point of contact identified within the company of the crossing company and the owner who has the responsibility to communicate about the safely managed crossing. There will be a cross and Company designated contact and an owner designated contact.
B) Is the entity that intends to install, operate, maintain a new pipeline that crosses existing pipeline facilities. The Crossing company may designate a third-party or parties to perform the task necessary to accomplish a Crossing but remains responsible for the work performed by such third parties.
C) Is the property in which a pipeline company and a landowner both have legal interest. The ROW is usually established through a written document known as an easement. The easement provides that each entity has the right to be there although each is permitted different uses of the land. Pipeline companies are typically granted permission to install operate and maintain a buried pipeline and sometimes, with surface apparatuses across a certain portion of land without interference with its rights to do so.
D) Is the construction of a new natural gas pipeline facility by Crossing company that will cross owners existing natural gas pipeline(s). The extent of the crossing area is established by the beginning and ending of the encroachment area. Crossing construction begins with the first disturbance of soil in the encroachment area and ends when the ROW has been restored.
4. SWP3
A) Storm Water Pollution Plan
B) Strategic Plan
C) Federal Water Pollution And Control Act
D) Reclaimed Water
5. What is the min stress relieving temp for ferritic alloy steels?
-1150 deg F
-1200 deg F
-1100 deg F
-1350 deg F
A) 1150 deg F
B) 1350 deg F
C) 1200 deg F
D) 1199 deg F
Solutions:
| Question # 1 Answer: B | Question # 2 Answer: D | Question # 3 Answer: C | Question # 4 Answer: A | Question # 5 Answer: C |