SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Sample Questions:
1. Which of the following are replenishment strategies for Kanban containers?
Note: There are 2 correct answers to this question.
A) Replenishment using process orders
B) Replenishment using reservations
C) Replenishment using direct transfer posting
D) Replenishment using planned independent requirements
2. What is the purpose of using a low level code?
Note: There are 2 correct answers to this question.
A) To determine the lowest explosion level at which a material occurs in all the product structures
B) To determine the priority of alternative components inside the material BOM (bill of material)
C) To determine the use of subitems inside the material BOM (bill of material)
D) To determine the sequence in which materials are planned in MRP
3. You want to set up a make-to-order planning scenario for a finished product. The bill of material contains two components: one should be procured for each sales order individually, and the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?
A) Choose planning strategy 20 (Make-to-Order) and select the corresponding Individual/Collective indicator
B) Choose planning strategy 50 (Planning without final assembly) and select the corresponding Individual/Collective indicator
C) Choose planning strategy 50 (Planning without final assembly) and select the corresponding Mixed MRP indicator
D) Choose planning strategy 20 (Make-to-Order) and select the corresponding Mixed MRP indicator
4. What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?
A) Sequencing on multi-activity resources is automatically updated during planning.
B) Operations on multi-resources are planned finitely in a sequence.
C) An operation is scheduled as close as possible to the desired date.
D) To create a slot, neighbouring operations are moved in both planning directions.
5. What are some advantages of using Kanban for material supply? Note: There are 2 correct answers to this question.
A) Material is only kept available in small quantities in production.
B) Replenishment is only triggered when components are required.
C) Material stock is built up for a long period of time in production.
D) Replenishment is always triggered on a regular basis.
Solutions:
| Question # 1 Answer: B,C | Question # 2 Answer: A,D | Question # 3 Answer: A | Question # 4 Answer: C | Question # 5 Answer: A,B |