IBM C4070-604 Exam Overview:
| Certification Vendor: | IBM |
|---|---|
| Exam Name: | IBM System z Technical V5 |
| Exam Number: | 000-604 (replaced by C4070-604) |
| Exam Format: | Multiple-choice |
| Passing Score: | 77% |
| Exam Duration: | 75 minutes |
| Available Languages: | Japanese, English |
| Exam Price: | Approx. $200 USD (varies by region) |
| Related Certifications: | IBM Certified Specialist - System z Technical |
| Real Exam Qty: | 57 |
| Certificate Validity Period: | 3 years |
| Recommended Training: | IBM Education - System z Technical Training |
| Exam Registration: | Pearson VUE IBM Program |
| Sample Questions: | IBM C4070-604 Sample Questions |
| Exam Way: | Proctored at Pearson VUE test centers; retired, no longer available for registration |
| Pre Condition: | Basic knowledge of mainframe concepts, System z architecture, and enterprise IT environments |
IBM C4070-604 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Installation & Post-Install Support | 25% | - Basic troubleshooting and support - Configuration and setup - Verification and validation - Pre-installation requirements |
| Topic 2: Apply Information, Installation Planning or Migration Considerations | 40% | - Migration strategies and considerations - Networking and connectivity planning - Logical Partitioning (LPAR) design - Specialty processors (IFL, zIIP, zAAP) |
| Topic 3: Evaluate & Establish Customer Environment and Plans | 35% | - System z hardware architecture and components - Capacity planning and sizing - Business and technical requirements analysis - zEnterprise and zBX concepts |
IBM System z Technical V5 Sample Questions:
Question 1
A z114 will be defined as a member of an ensemble and use Unified Resource Manger. Which of the following options correctly describe the HMC requirements?
A. a Z114 requires no HMC
B. Both the Primary HMC and Alternate HMC must have various identical components
C. Requires a primary HMC only
D. Any HMC may be carried forward
Question 2
A System z FTSS needs POWER blades configured for a zBX. Which of the following procedures should be used for this configuration?
A. The z FTSS configures all components for the zBX using zManager configuration tool
B. POWER team should configure the blade type normally acquired by the customer for a BladeCenter
C. The customer should configure through the IBM Workload Estimator
D. The z FTSS should provide the POWER blade requirements to the POWER team
Question 3
A customer will be upgrading their z10 EC to a z196 and would like to position the z196 to take advantage of new PCIe infrastructure for future support. Currently they have two I/O cages. The customer cannot take a future outage to add the new drawer. Which of the following will position the server for future use of a PCIe I/O drawer?
A. Just perform the upgrade, the existing cards will carry forward into the new PCIe drawer.
B. The new PCIe drawer cannot be installed concurrently so order the new PCIe OSA-Express4S 10GbE and/or FICON Express8S cards now which will drive the new PCIe drawer.
C. Order the new PCIe OSA-Express4S 1000BaseT and/or FICON Express4S cards now which will drive the new PCIe drawer.
D. The drawer can be added later when the customer is ready to order the new PCIe cards.
Question 4
Once the sale of a System z has been made, which of the following individuals is responsible to ensure that the implementation plan is executed?
A. IBM or Business Partner Technical Specialist
B. IBM Installation Planning Representative
C. IBM or Business Partner TDA Leader
D. IBM or Business Partner Client Representative
Question 5
A customer is looking for a solution that delivers a workload management across the platforms that run his core application. Additionally he is interested in a continuous availability solution that controls all components of the application independent of the platform that is used for the deployment. Which of the following makes zEnterprise the best match to those requirements?
A. The new Infiniband coupling link of z196 offer the opportunity to interconnect all platforms. The Unified Resource Manager delivers a central tool to control all events.
B. The customer can consolidate all application parts either on z/OS or on Linux on System z to meet the requirements.
C. The combination of Unified Resource Manager, GDPS and TSAMP meets all requirements without changes to the applications.
D. z/OS offers with Parallel Sysplex and WLM a best of breed solution. For the distributed part Tivoli System Automation for Multi Platforms (TSAMP) delivers the required functionality.
Solutions:
| Question 1 Answer: B | Question 2 Answer: D | Question 3 Answer: D | Question 4 Answer: A | Question 5 Answer: C |
We're so confident of our products that we provide no hassle product exchange.


By Cornelius