APICS CPIM Certification Exam is an excellent way for professionals to demonstrate their knowledge and expertise in the field of supply chain management. Certified in Production and Inventory Management certification is highly regarded by employers and can lead to increased job opportunities and higher salaries. Additionally, the knowledge gained through the certification process can help professionals become more effective in their roles and contribute to the success of their organizations.
NEW QUESTION # 14
A work center is available 120 hours but actually produced goods for 100 hours. What is the utilization of the work center?
- A. 83.5%
- B. 84%
- C. 84.3%
- D. 83.3%
Answer: D
NEW QUESTION # 15
products. is concerned with the production of high-volume standard
- A. Repetitive manufacturing
- B. Continuous manufacturing
- C. Flow manufacturing
- D. None of the above
Answer: C
NEW QUESTION # 16
The places where carriers load and unload goods to and from vehicles and make connections between local pickup and delivery service and line-haul service are called:
- A. Workstations
- B. Mortals
- C. Terminals
- D. None of the above
Answer: C
NEW QUESTION # 17
The Question mark represents:
- A. Payables
- B. None of these
- C. Inventories
- D. Cost of goods solved
Answer: C
NEW QUESTION # 18
Production planning includes;
- A. All of these
- B. Material Requirement planning and capacity planning
- C. Master planning
- D. Forecasting
Answer: A
NEW QUESTION # 19
Find methods to maximize the utilization of the constraint toward productive throughput is called:
- A. Manage constraint
- B. None of the above
- C. Exploit constraint
- D. Utilize constraint
Answer: C
NEW QUESTION # 20
When the last operation is on the routing is scheduled first and is scheduled for complete at the due date, this is called:
- A. Rearward scheduling
- B. Timid scheduling
- C. Self-assistant scheduling
- D. Backward scheduling
Answer: D
NEW QUESTION # 21
The formula to calculate the rated capacity is:
- A. Rated capacity = available time * utilization * efficiency
- B. Rated capacity = expected time * number of workers * efficiency
- C. Rated capacity = available time * performance * efficiency
- D. Rated capacity = actual time * utilization * efficiency
Answer: C
NEW QUESTION # 22
are best used for forecasting products with stable demand where there is little trend or seasonality.
- A. Estimated calculations
- B. Moving averages
- C. None of the above
- D. Demand averages
Answer: B
NEW QUESTION # 23
Control is exercised through individual items in a particular inventory, this is called:
- A. Inventory element
- B. Stock entity
- C. Inventory corps
- D. Stock-keeping units
Answer: D
NEW QUESTION # 24
The formula for the planned backlog for period 1 is calculated as:
- A. Planned backlog for period 1 = Planed backlog + previous output - planned output
- B. Planned backlog for period 1 = Previous backlog + planned input - planned output
- C. Planned backlog for period 1 = Planed backlog + previous input - planned output
- D. Planned backlog for period 1 = Actual backlog + planned input - actual output
Answer: B
NEW QUESTION # 25
The files contained in the database are of two types which are:
- A. fixed and variable
- B. absolute and relative
- C. planning and control
- D. planning and procedural
Answer: C
NEW QUESTION # 26
Altering the load in balancing capacity available means?
- A. Rescheduling of load sheet
- B. Shifting orders back
- C. Shifting orders ahead or back
- D. Shifting orders ahead
Answer: C
NEW QUESTION # 27
Some of the characteristics customers expect when they buy products are all of the following EXCEPT:
- A. Delivery lead time
- B. A fair price with higher quality products and services
- C. Product and volume flexibility
- D. Presale services better than after sale services
Answer: D
NEW QUESTION # 28
A company wants to minimize the cost of manufacture and also be flexible enough to adapt to changing needs. Changes to production schedules can result in the following EXCEPT:
- A. Process create more scraps than needed than needed
- B. Loss of credibility for the MPS and the planning process
- C. Cost increases due to rerouting, rescheduling, extra setups, expediting, and buildup of work-in-process inventory
- D. Decreased customer service. A change in quantity of delivery can disrupt the schedule of other orders
Answer: A
NEW QUESTION # 29
Capacity needs to be measured on following levels EXCEPT:
- A. Work center
- B. Plant, which can be considered as a group of different work centers
- C. Machine or individual
- D. None of these
Answer: D
NEW QUESTION # 30
Planning bill does not represent
- A. Average product
- B. Buildable products
- C. Product structure looks
- D. None of the above
Answer: B
NEW QUESTION # 31
What includes the functions of establishing specifications, selecting suppliers, price determination, and negotiation?
- A. Procurement
- B. Competitive follow-up
- C. Supplier scheduling
- D. None of the above
Answer: A
NEW QUESTION # 32
Demonstrated capacity is:
- A. Average Output
- B. Minimum output
- C. None of these
- D. Maximum output
Answer: A
NEW QUESTION # 33
Production activity control in intermittent manufacturing is complex Because of:
- A. The variety of routing
- B. Scheduling problems
- C. All of the above
- D. The number of products made
Answer: C
NEW QUESTION # 34
Which one of the following is a basic strategy to achieve the level of shortest lead time?
- A. Make-to-stock
- B. Assemble-to-order
- C. None of these
- D. Engineer-to-order
Answer: C
NEW QUESTION # 35
If the opening inventory is 400 units, demand is 900 units, and production is 800 units, what will be the ending inventory?
- A. 200 units
- B. 400 units
- C. 350 units
- D. 300 units
Answer: D
NEW QUESTION # 36
Qualitative techniques are productions based on judgment, intuition, and informed opinions.
- A. True
- B. False
Answer: A
NEW QUESTION # 37
......
Share Latest CPIM DUMP Questions and Answers: https://www.surepassexams.com/CPIM-exam-bootcamp.html
PDF Dumps 2024 Exam Questions with Practice Test: https://drive.google.com/open?id=1XgQmuslHSrYAu2EXPhgB7cHqX3uEVn7m