NEW QUESTION 179
Which process is used to define how baselines will be established and controlled?

  • A. Starting up a project
  • B. Directing a project
  • C. Initiating a project
  • D. Controlling a stage

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Quality

 

NEW QUESTION 180
Which is a minimum requirement when applying the business case theme?

  • A. To define the management actions required to ensure the project's outcomes are achieved
  • B. To specify the solution to be used to deliver the business option selected
  • C. To integrate the benefits management approach with the project and stage plans
  • D. To ensure the corporate business plan is updated with the project costs and benefits

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 181
Which is a benefit of using PRINCE2?

  • A. Includes many of the proven planning techniques, such as critical path analysis
  • B. Can be used to manage both projects and programmes
  • C. Is a method specifically designed for technical projects
  • D. Provides for the efficient and economic use of management time

Answer: D

 

NEW QUESTION 182
What is an off-specification?

  • A. A new requirement
  • B. A major risk
  • C. A type of issue
  • D. A quality tolerance

Answer: C

Explanation:
Section: Volume A

 

NEW QUESTION 183
Which is part of quality control?

  • A. Produce quality records to show that the planned quality activities have been carried out
  • B. Maintain the corporate organization's quality management system
  • C. Define the quality responsibilities of those involved in the production of the products
  • D. Document the project's acceptance criteria in the Project Product Description

Answer: A

 

NEW QUESTION 184
What is a supplier of a PRINCE2 project responsible for?

  • A. Providing the project mandate
  • B. Realizing the benefits from the project
  • C. Providing resources to deliver the project outputs
  • D. Establishing the project's governance

Answer: C

Explanation:
Explanation
Reference http://prince2.wikidot.com/senior-supplier

 

NEW QUESTION 185
Which is a minimum requirement for applying the change theme?

  • A. To record every issue that is raised in the issue register
  • B. To establish a change budget to fund changes in scope
  • C. To appoint the project manager as part of the change authority
  • D. To define the project's approach to baselining products

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Themes#Change_Theme

 

NEW QUESTION 186
Which describes a project benefit?

  • A. The result of a change derived from using the project's products
  • B. A measurable improvement resulting from an outcome
  • C. An uncertain result caused by project actions
  • D. A specialist product of the project

Answer: B

 

NEW QUESTION 187
Which is a FALSE statement about technical stages?

  • A. Typified by the use a particular set of specialist skills
  • B. Can span more than one management stage
  • C. Include the Managing a Stage Boundary process activities
  • D. Can overlap with other technical stages

Answer: C

 

NEW QUESTION 188
When is the 'managing a stage boundary' process used?

  • A. Near the end of delivery stages
  • B. Near the end of each stage
  • C. Immediately after the project board has authorized the next stage
  • D. Immediately alter the project board has authorized the previous stage

Answer: A

 

NEW QUESTION 189
Which is NOT a purpose of the Initiating a Project process?

  • A. Establish solid foundations for a project
  • B. Enable a Project Boarddecision about the commitment of resources to a project
  • C. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
  • D. Enable the Project Board to decide whether it is worthwhile to initiate a project

Answer: D

 

NEW QUESTION 190
Which is a recommended quality review team role?

  • A. Administrator
  • B. Assurance
  • C. Project Manager
  • D. Project Support

Answer: A

 

NEW QUESTION 191
What is the project manager role responsible for?

  • A. Defining the project-level tolerances
  • B. Approving the completion of each management stage
  • C. Ensuring that the project produces the required products
  • D. Verifying that the project gives value for money

Answer: C

Explanation:
Explanation
Reference http://prince2.wiki/Project_Manager

 

NEW QUESTION 192
Where should a team manager look for information about the quality required for a product?

  • A. Project initiation documentation
  • B. Team plan
  • C. Quality management approach
  • D. Product description

Answer: D

Explanation:
Reference http://prince2.wiki/Quality#The_Quality_Knowledge_provided_by_PRINCE2

 

NEW QUESTION 193
Which is a minimum requirement when applying the business case theme?

  • A. To define the management actions required to ensure the project's outcomes are achieved
  • B. To specify the solution to be used to deliver the business option selected
  • C. To integrate the benefits management approach with the project and stage plans
  • D. To ensure the corporate business plan is updated with the project costs and benefits

Answer: B

 

NEW QUESTION 194
Which role is part of the Project Board?

  • A. Corporate or programme management
  • B. Senior Supplier
  • C. Risk owner
  • D. Project Manager

Answer: B

 

NEW QUESTION 195
Which is a purpose of the Initiating a Project process?

  • A. Decide on the project approach
  • B. Decide if it is worthwhile to initiate a project
  • C. Identify the number of Work Packages required
  • D. Establish solid foundations for a project

Answer: D

 

NEW QUESTION 196
Which role is responsible for creating Checkpoint Reports?

  • A. Senior Supplier
  • B. Team Manager
  • C. Project Support
  • D. Change Authority

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 197
During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

  • A. Project Plan
  • B. Team Plan
  • C. Work Package
  • D. End Stage Report

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 198
Which process monitors work that has been assigned to a team manager?

  • A. Directing a project
  • B. Managing a stage boundary
  • C. Managing product delivery
  • D. Controlling a stage

Answer: C

Explanation:
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-process-managing-product-delivery.php

 

NEW QUESTION 199
How does the project board use the 'manage by stages' principle to control the project?

  • A. By reviewing project viability at defined intervals
  • B. By ensuring that the benefits are managed and controlled
  • C. By reviewing previous project closure documentation
  • D. By approving the project management team

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Manage_by_stages

 

NEW QUESTION 200
......


PRINCE2-Foundation Exam Certification Path

We are giving a flexible alternative to pay via PayPal where you can make payment using a credit card, and you may have concerns on how you can purchase our PRINCE2 bills. You may check their website for further information on that payment if you purchase from a nation like India. Once you have completed your purchase, do not worry, our services are not used to stop only following the sale of one of these products, and we offer after sales services just as PRINCE2-Foundation exam dumps is always updated to your profile because we use the review PRINCE2-Foundation practice exams for regular updating. You will have multiple options in order to get the information from the exam dumps we provide first, you will access the dump through an online exam simulator, where all questions and answers can be put into practice, which provide you with plenty of insight as to how you are doing, how many you scored during your attempt to do so. The second way to access our bought exam dumps is through mobile applications, we have a mobile application that you can download from the App Store, play store, and just log in and use your login and password. If you feel you need some help from our team, we're going to give you priority because we believe in delivering customer service and happiness, and you'll contact us by simply dropping email.

 

Actual PRINCE2Foundation Exam Recently Updated Questions with Free Demo: https://www.surepassexams.com/PRINCE2Foundation-exam-bootcamp.html

Valid PRINCE2Foundation exam with PRINCE2 Real Exam Questions: https://drive.google.com/open?id=1Ts1E2wzGkad-9Yb5IXJWT1x49qKgnJdN