SAP C-TS422-2601 Exam Overview:
| Certification Vendor: | SAP |
|---|---|
| Exam Name: | SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing |
| Exam Number: | C-TS422-2601 |
| Related Certifications: | SAP Certified Associate - SAP S/4HANA Production Planning and Manufacturing |
| Passing Score: | 64% |
| Exam Price: | $541 USD |
| Exam Duration: | 180 minutes |
| Real Exam Qty: | 80 - 100 |
| Certificate Validity Period: | 12 months |
| Exam Format: | Multiple choice, Performance-based tasks, Multiple response, Scenario-based |
| Available Languages: | Japanese, French, English, Spanish, German, Chinese |
| Recommended Training: | TS422 - SAP S/4HANA Production Planning and Manufacturing II TS421 - SAP S/4HANA Production Planning and Manufacturing I |
| Exam Registration: | SAP Certification Shop |
| Sample Questions: | SAP C-TS422-2601 Sample Questions |
| Exam Way: | Online proctored or Onsite at SAP authorized test centers; open-book allowed |
| Pre Condition: | Basic knowledge of SAP S/4HANA navigation and manufacturing processes; recommended completion of courses TS421 and TS422 |
| Official Syllabus URL: | https://training.sap.com/certification/c_ts422_2601-sap-certified-associate---sap-s-4hana-cloud-private-edition-production-planning-and-manufacturing/ |
SAP C-TS422-2601 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Demand Management | < 8% | - Demand Strategies - Planned Independent Requirements |
| Topic 2: Process Orders | < 8% | - Master Data for Process Manufacturing - Process Order Management |
| Topic 3: Production Orders | 12% - 18% | - Order Settlement and Closing - Order Creation and Structure - Order Release and Execution - Availability Check and Capacity Check |
| Topic 4: Lean Manufacturing and Kanban | 8% - 12% | - Kanban Process and Setup - Repetitive Manufacturing |
| Topic 5: Material Requirements Planning (MRP) | 8% - 12% | - MRP Types and Parameters - Procurement Proposals - MRP Logic and Planning Run |
| Topic 6: Advanced Planning (PP/DS) | 8% - 12% | - Heuristics and Planning Functions - Pegging and Alerts |
| Topic 7: Capacity Planning | 8% - 12% | - Finite Scheduling Concepts - Capacity Evaluation - Capacity Leveling and Scheduling |
| Topic 8: Master Data in SAP S/4HANA | 12% - 18% | - Material Master Data - Work Centers and Routings - Production Versions - Bill of Materials (BOM) |
| Topic 9: Integration and Analytics | 10% - 15% | - Integration with Finance / Controlling - Manufacturing Reporting and Analytics |
SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing Sample Questions:
Question 1
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching?
Note: There are 2 correct answers to this question.
A. Move time
B. Teardown time
C. Setup time
D. Queue time
Question 2
What could be the reason for different combinations of components in a multiple bill of material (BOM)?
Note: There are 2 correct answers to this question.
A. BOM component status
B. BOM header status
C. Lot size
D. Manufacturing date
Question 3
Advanced Planning uses master data from SAP S/4HANA Cloud Private Edition.
In which data objects can you set the Advanced Planning flag?
Note: There are 2 correct answers to this question.
A. Material
B. Work center
C. Plant
D. Production version
Question 4
Your production planners are allowed to execute planning only for specific resources. How can you achieve this in Advanced Planning (PP/DS)?
A. Use a planning area.
B. Use a propagation range.
C. Use a resource group.
D. Use a planning group.
Question 5
Your company manufactures materials whose characteristics differ for each manufacturing process. Which application do you have to use in SAP S/4HANA Cloud Private Edition to be able to track use this information in all areas of logistics?
A. Quality management
B. Engineering change management
C. Batch management
D. Process order management
Solutions:
| Question 1 Answer: A,D | Question 2 Answer: C,D | Question 3 Answer: A,B | Question 4 Answer: C | Question 5 Answer: C |