350-601 Practice Test Questions Answers Updated 139 Questions
350-601 dumps & CCNP Data Center Sure Practice with 139 Questions
Recommended Course: Implementing and Operating Cisco Data Center Core Technologies (DCCOR) v1.0
This course is designed to help candidates prepare for high-level roles in the data center by acing test 350-601. It focuses on what you need to know to execute compute for data center, SAN and LAN architecture. Besides, it gives in-depth coverage of the basics of security and automation in various data centers. Through hands-on lab environments and interactive lectures, you will understand how to put into practice, operate, secure, and support the Cisco data center architecture such as the Cisco Unified Computing System, Nexus Switches, and MDS Switches. The vendor designed this training with all the candidates’ needs in mind, thus it's easy to see why it is offered in as many as 3 modes. These include the eLearning option, classroom learning, and instructor-led classes. Regardless of the chosen mode of training, this course is intended to run for a maximum of eight days. The instructor-led training alone combines 5 days of intense hands-on lab training with another 3 of self-paced studying. Similarly, the virtual instructor-led training involves 5 days of web-based training plus another 3 of studying with self-paced resources. Lastly, the eLearning mode only features a comprehensive 8-day training using exciting challenges, practice, and videos. By preparing for the official exam using this course, you will not only be ready to test yourself with the industry’s best materials but also get prepared to hold a variety of exciting data center roles at the professional and expert levels.
Career Path
You can take the Cisco 350-601 exam to qualify for as many as three certificates as mentioned above. So, the next path will depend on your goals. If you are at the intermediate level, the best certificate to opt for is Cisco CCNP Data Center. But if you take this exam to attain the CCIE Data Center accreditation, you may want to seek a new challenge by focusing on a completely different path since it has a lab exam.
NEW QUESTION 66
Refer to the exhibit.
What is the result of implementing this configuration?
- A. The timeout value on the TACACS+ server is 10 seconds.
- B. The TACACS+ server uses the type-6 encrypted format.
- C. The switch queries the TACACS+ server by using an encrypted text PAP login.
- D. The switch queries the TACACS+ server by using a clear text PAP login.
Answer: D
NEW QUESTION 67
DRAG DROP
An engineer is configuring VNTag between a virtualized server and a Cisco Nexus 5500 Series switch.
Drag and drop the configuration steps from the left into the correct order on the right.
Select and Place:
Answer:
Explanation:
Section: Compute
Explanation/Reference:
https://www.cisco.com/c/en/us/td/docs/switches/datacenter/nexus5500/sw/adapter-fex/6x/ b_5500_Adapter_FEX_Config_6x/b_5500_Adapter_FEX_Config_602N11_chapter_010.html
NEW QUESTION 68
An engineer is implementing security on the Cisco MDS 9000 switch. Drag drop the descriptions from the left onto the correct security features on the right.
Answer:
Explanation:
Explanation
prevent unauthorized - fabric binding.
Uses the exchange fabric membership- fabric binding
Can be distributed - port security
Allows a preconfigured - port security
NEW QUESTION 69
A POAP-enabled Cisco Nexus switch will not enter POAP mode. Which two conditions should be verified?
(Choose two.)
- A. The license file is missing on the switch.
- B. No Cisco NX-OS image is present on the bootflash.
- C. Bootflash must contain a special directory named POAP with poap.py file.
- D. No startup configuration is available.
- E. The switch is in bootup process.
Answer: A,C
NEW QUESTION 70
Refer to the exhibit.
What is the result of implementing this configuration?
- A. The TACACS+ server uses the type-6 encrypted format.
- B. The switch queries the TACACS+ server by using an encrypted text PAP login.
- C. The timeout value on the TACACS+ server is 10 seconds.
- D. The switch queries the TACACS+ server by using a clear text PAP login.
Answer: C
Explanation:
Section: Security
NEW QUESTION 71
An engineer must shut down the Ethernet 1/2 interface when the Ethernet 4/5 interface state is down. Drag and drop the CLI commands from the bottom onto the blanks in the exhibit to implement this EEM. Not all commands are used.
Answer:
Explanation:

NEW QUESTION 72
Refer to the exhibit.
A network engineer is setting up a multihomed OTV network. The first site has been set up with a primary and secondary adjacency server.
Which configuration must be added on the remote OTV AEDs site?
- A. Option A
- B. Option B
- C. Option C
- D. Option D
Answer: C
NEW QUESTION 73
Refer to the exhibit.
An engineer is configuring a VSAN on the network Which option must be selected to create the VSAN?
- A. Fabric B
- B. Fabric A
- C. FC Zoning Enabled
- D. Common/Global
Answer: B
NEW QUESTION 74
Refer to the exhibit.
What is a characteristic of the UUID in the service profile presented.
- A. allocated from a UUID pool
- B. vendor assigned
- C. based on the hardware
- D. unique system generated
Answer: A
NEW QUESTION 75
Drag and drop the characteristics from the left onto the NAS protocols on the right. Some characteristics are used more than once
Answer:
Explanation:

NEW QUESTION 76
Refer to the exhibit.
An engineer configures FCIP on a Cisco MDS 9000 Series switch. What is the result of implementing the configuration?
- A. Mode2 is enabled by default.
- B. Compression is performed by using software.
- C. Compression is performed by using hardware
- D. The switch attempts to make two TCP connections
Answer: C
NEW QUESTION 77
Which two actions should be taken before an upgrade is started on a Cisco MDS switch? (Choose two.)
- A. back up the configuration
- B. free up space on the USB3 device by deleting old Cisco NX-OS image files
- C. disable Cisco Fabric Services
- D. make the primary supervisor the active supervisor
- E. check the impact of the upgrade using the show install all impact command
Answer: A,E
NEW QUESTION 78
Refer to the exhibit.
An engineer is implementing zoning on two Cisco MDS switches. After the implementation is finished, E Ports that connect the two Cisco MDS switches becomes isolated. What is wrong with the implementation?
- A. E Ports on both MDS switches must be configured as F ports for the zoning to function.
- B. Different zone set names must be configured on both MDS switches.
- C. Zones are local to the MDS switch and name service must be used to activate the connection between E ports.
- D. Zones must have the same name on both MDS switches for the E ports to function.
Answer: D
NEW QUESTION 79
Multiple roles are applied to a user on the Cisco MDS 9000 Series Switch.
Which statement is true?
- A. The first role assigned takes precedence over subsequent roles.
- B. Access to a command takes priority over being denied access to a command.
- C. Any commands that have conflicting settings between roles are denied.
- D. The last role assigned takes precedence over previous roles.
Answer: B
Explanation:
Section: Compute
Explanation/Reference:
NEW QUESTION 80
An engineer is seeking the most optimal on demand CPU performance while configuring the BIOS settings of UCS C-series rack mount server.
- A. C6 non-Retention
- B. C2 state
- C. C6 Retention
- D. C0/C1 state
Answer: A
NEW QUESTION 81
Refer to the exhibit.
An engineer must monitor all LAN traffic on Fabric A from a blade server. Which source should be configured in the test-span monitor session to complete this task?
- A. all vHBAs from the service profile that correspond to this server
- B. all vNICs from the service profile that correspond to this server
- C. all uplink FCoE ports
- D. all uplink Ethernet ports
Answer: B
Explanation:
Explanation
https://www.cisco.com/en/US/docs/unified_computing/ucs/sw/gui/config/guide/141/UCSM_GUI_Configuration
NEW QUESTION 82
An engineer is implementing FCoE. Which aspect of DCBXP on a Cisco Nexus switch affects this implementation?
- A. It uses the Cisco Fabric Services protocol to exchange parameters between two peer links.
- B. It provides the authentication of peers on the Cisco Nexus switch.
- C. It always is enabled on 10/100-Mbps native Ethernet ports.
- D. It requires that LLDP transmit and LLDP receive are enabled on the FCoE interface.
Answer: D
NEW QUESTION 83
An engineer is configuring VNTag between a virtualized server and a Cisco Nexus 5500 Series switch. Drag and drop the configuration steps from the into the correct order on the right.
Answer:
Explanation:
Explanation
install the virtualization feature set
Enable the virtualization feature set
Configure the port profile
Configure support for VNTag mode on the interface that connects to the server.
Configure the server to support NIV mode
Configure the vNICs of the server
NEW QUESTION 84
Refer to the exhibit.
Which action must be taken before the maintenance policy can be committed?
- A. Associate a service profile to the maintenance policy.
- B. Set the policy to apply the change on the next reboot.
- C. Specify a maintenance time by selecting a schedule.
- D. Set the soft shutdown timer to a specific time.
Answer: D
NEW QUESTION 85
An engineer is asked to use SaaS to manage Cisco computing. Which two items are needed to accomplish the task? (Choose two.)
- A. Intersight
- B. UCS Central
- C. UCS Manager
- D. Device/Claim ID
- E. Node name/Serial Number
Answer: A,C
NEW QUESTION 86
An engineer needs to make an XML backup of Cisco UCS Manager The backup should be transferred using an authenticated and encrypted tunnel and it should contain all system and service profiles configuration Which command must be implemented to meet these requirements?
- A. Option A
- B. Option B
- C. Option C
- D. Option D
Answer: C
Explanation:
https://www.cisco.com/en/US/docs/unified_computing/ucs/sw/cli/config/guide/1.4.1/CLI_Config_Guide_1_4_1_chapter40.html
NEW QUESTION 87
An engineer must configure HTTPS secure management for Cisco UCS Manager using a key ring named kr2016 and a key size of 1024 bits. The environment consists of a primary fabric interconnect named UCS-A and a secondary fabric interconnect named UCS-B. Which command sequence must be used to accomplish this goal?
- A. Option B
- B. Option A
- C. Option C
- D. Option D
Answer: A
Explanation:
Explanation
https://www.cisco.com/en/US/docs/unified_computing/ucs/sw/cli/config/guide/1.4.1/CLI_Config_Guide_1_4_1_
NEW QUESTION 88
An engineer deploys a custom guest shell rootfs onto multiple switches. Drag and drop the steps from the left into the correct order on the right.
Answer:
Explanation:
Explanation
export the guest shell rootfs step 1
store it in a file server step 2
Customize the guest shel rootfs step 3
import the guest shell rootfs to other switches step 4
install the specific guest shell across devices simultaneously step 5
NEW QUESTION 89
......
New 350-601 Exam Questions| Real 350-601 Dumps: https://www.surepassexams.com/350-601-exam-bootcamp.html
Get New 350-601 Certification – Valid Exam Dumps Questions: https://drive.google.com/open?id=1LekuMyKq-xDI1kRqCHA6itbsh_GR3SvY