NEW QUESTION # 72
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  • A. Front end loading.
  • B. Multiple calendars.
  • C. Preferential logic.
  • D. Start and finish constraints.

Answer: A


NEW QUESTION # 73
These are the activities on the critical path:

  • A. A, D, & I.
  • B. A, B, G, & H.
  • C. A, C, E, & H.
  • D. A, B, F, & J

Answer: B


NEW QUESTION # 74
What problems can a soils engineer deal with on a project?

  • A. Survey error.
  • B. Archeological findings.
  • C. Toxic soils.
  • D. Hidden subsurface conditions.

Answer: D


NEW QUESTION # 75
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

  • A. It is on the critical path.
  • B. Was completed in the past.
  • C. Is a milestone.
  • D. Has yet to be completed.

Answer: D


NEW QUESTION # 76
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

  • A. Productivity efficiency.
  • B. Acceleration.
  • C. Production output.
  • D. Productivity loss.

Answer: D


NEW QUESTION # 77
What is the cycle time?

  • A. 6 minutes
  • B. 17 minutes
  • C. 5 minutes
  • D. 14 minutes

Answer: B


NEW QUESTION # 78
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

  • A. 14.
  • B. 12.
  • C. 13.
  • D. Cannot be determined.

Answer: B


NEW QUESTION # 79
Budgeted cost of work scheduled is _______________________.

  • A. The sum of all budgets for work scheduled to be accomplished within a given time period
  • B. The expected total cost of an activity, group of activities or the project
  • C. The value of the completed work expressed in terms of the budget assigned to that work
  • D. The total authorized budget for accomplishing the project scope

Answer: B


NEW QUESTION # 80
Which of the following is NOT required when initially planning a project?

  • A. Logical relationships between the tasks.
  • B. Resource Identification and leveling.
  • C. The duration of each task.
  • D. A schedule that identifies tasks required on a project.

Answer: C


NEW QUESTION # 81
What activities are concurrent to Activity 2001 in the "normal" schedule?

  • A. 7001.
  • B. 1000.
  • C. 1001.
  • D. 2003.

Answer: A


NEW QUESTION # 82
What was the original planned duration for Activity A through Activity G?

  • A. 24.
  • B. 28.
  • C. 26.
  • D. 25.

Answer: B


NEW QUESTION # 83
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

  • A. Use the forward-looking critical path of the most current updates.
  • B. Use the progressed portion of the critical path of the baseline schedule.
  • C. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
  • D. Use the progressed portion of the critical path of all the updates previous to the current update.

Answer: A


NEW QUESTION # 84
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

  • A. 37.
  • B. 36.
  • C. 42.
  • D. 40.

Answer: B


NEW QUESTION # 85
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

  • A. Non-excusable delay
  • B. Compensable delay
  • C. Non-compensable delay
  • D. Excusable delay

Answer: C


NEW QUESTION # 86
Determine the correct formula and date for the late finish for Activity 9004.

  • A. LS.10002 + 1 day -> 11-29-03.
  • B. LS.10002 - Lag.7 - l day -> 11-20-03.
  • C. LS.10002 - 1 day -> 11-27-03.
  • D. LS.10002^ Lag.7 + i day -> 11-20-03.

Answer: D


NEW QUESTION # 87
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

  • A. It is calculated using logic reflecting out-of-sequence progress.
  • B. There is no such thing.
  • C. It is calculated using the original logic.
  • D. An out-of-sequence activity cannot resume until all predecessors are finished.

Answer: C


NEW QUESTION # 88
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

  • A. 193 days
  • B. 183 days
  • C. 91 days
  • D. 168 days

Answer: B


NEW QUESTION # 89
Free float is the

  • A. Difference between the early finish dates and late finish dates of an activity.
  • B. Difference between the early dates and late dates of an activity.
  • C. Difference In float value of the critical path activities and the float value of the specific activity being analyzed.
  • D. Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.

Answer: D


NEW QUESTION # 90
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

  • A. C.
  • B. B.
  • C. S.
  • D. W.

Answer: C


NEW QUESTION # 91
What owner action could have mitigated the late completion of the project?

  • A. Use a procurement agent to monitor and expedite equipment deliveries.
  • B. Self-perform more of the work.
  • C. Hire a more senior project manager.
  • D. Prepare better structural steel drawings.

Answer: A


NEW QUESTION # 92
The work breakdown structure is used to organize

  • A. The smallest defined work packet
  • B. Similar activity coding of schedule activities
  • C. The chart of accounts
  • D. "Smart activity ID codes" representing similar items of scheduled work

Answer: A


NEW QUESTION # 93
......