NEW QUESTION # 47
You are managing a project based on a Waterfall model. You define a project and a project plan in Oracle Project Management with tasks and subtasks applicable to each of the phases of the project: Initiation, Discovery, Design, Build, Test, and Deploy. As a project manager, you want to define deliverables for your project requirements that are elucidated during the Discovery phase of your project. You now want to understand how the inheritance between requirements, tasks, and deliverables works.
Which two are correct statements in this scenario?

  • A. A deliverable associated with a requirement is automatically associated with the tasks created for that requirement.
  • B. A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement.
  • C. The association of a deliverable with a task is dependent on associating a requirement with a task.
  • D. You associate a deliverable with a task independent of associating a requirement with a task.

Answer: B

Explanation:
According to Oracle sources1, the inheritance between requirements, tasks, and deliverables works as follows:
You can associate a deliverable with a task independent of associating a requirement with a task. You can also associate a deliverable with a requirement independent of associating a task with a requirement1.
A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement. You must manually associate the deliverable with the tasks that produce it1.
Therefore, the correct answer is B and D.
1: Can deliverables for projects and tasks be inherited from associated requirements? - docs.oracle.com (index 1) In Oracle Project Management, you can define requirements, tasks, and deliverables for your project based on your project methodology and lifecycle. Requirements are statements of needs or expectations that must be met by the project outcome. Tasks are units of work that must be performed to complete the project. Deliverables are products or services that are produced or provided as part of a task or requirement. Two correct statements about how the inheritance between requirements, tasks, and deliverables works are:
You associate a deliverable with a task independent of associating a requirement with a task. This means that you can create a deliverable for a task regardless of whether the task is linked to a requirement or not.
A deliverable associated with a requirement is not automatically associated with the tasks created for that requirement. This means that you have to manually associate a deliverable with a task even if both the deliverable and the task are linked to the same requirement.


NEW QUESTION # 48
Your customer accounts revenue based on, product class category. Because all your customer''s projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category "Funding Source" and assign it to all projects. However, you notice that the accounting is still happening based on product class category. Identify the reason for this problem. (Choose the best answer.)

  • A. Funding source class category is not enabled for "available as accounting source".
  • B. Product class category is not enabled for "available as accounting source".
  • C. Funding source class category is assigned to all project types.
  • D. Funding source class category is enabled for "available as accounting source".

Answer: A

Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-foundation-configuration-define-types-and-categorizations.html#OAPFM222700 Topic - Manage Project Class Categories Setting Up Class Categories: Points to Consider Available as Accounting Source This option indicates if the class category is available as an accounting source so that Oracle Fusion Subledger Accounting can use the category to create mapping sets, account rules, journal line rules, and description rules.
Only one class category at a time is available as an accounting source in Oracle Fusion Subledger Accounting. To change the class category that Oracle Fusion Subledger Accounting uses, deactivate the old class category and create a new one with a different date range.


NEW QUESTION # 49
Which three features are part of Oracle Fusion Functional Setup Manager?

  • A. updating an implementation project task list by changing the opt-in configuration to suit the latest requirements
  • B. modifying an existing implementation project task list by selecting more functional areas when needed
  • C. guided task list for end-to-end setup requirements
  • D. export and import services for setup data migration between environments
  • E. feature opt-in for a best fit configuration

Answer: D

Explanation:
https://docs.oracle.com/en/cloud/saas/applications-common/r13-update17d/oafsm/applications-cloud-using-functional-setup-manager.pdf Functional Setup Manager offers the following:
*Standardized application configuration and setup experience
*Feature opt-in for a best fit configuration
*xible processes for managing setup:
*Setup by functional areas for an adopt-as-you-go approach
*Implementation projects to manage setup
*Upload file to enter setup data in bulk
* Guided task list for end-to-end setup requirements
* Export and import services for setup data migration between environments
* Comprehensive reporting on setup data


NEW QUESTION # 50
Your business user has created a purchase order (PO) that has the following attributes:
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the "Import and Process Cost transactions" ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that there is no cost transferred to the projects. Identify two reasons for this problem.

  • A. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to NO, cost is transferred to projects by receipt accounting.
  • B. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to projects only if there are accounted receipt lines.
  • C. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to Yes, cost is transferred to project by payables.
  • D. When you have an AP invoice that is matched against a PO with Accrue at Receipt set to YES, cost is transferred to projects by Cost Management and not by Payables.

Answer: A

Explanation:
When the Accrue at Receipt option is set to Yes on a PO, the cost of the items or services is accrued when they are received, not when they are invoiced. Therefore, the cost is transferred to projects by Cost Management and not by Payables. However, if the PO is closed for receiving without creating a receipt, there will be no accounted receipt lines and no cost will be transferred to projects. To transfer the cost to projects, you need to either create a receipt or reopen the PO for receiving. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-costs.html#OAPFM2355855


NEW QUESTION # 51
Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.
Identify the correct statement about the RBS and new resources. (Choose the best answer.)

  • A. If the "Allow resource changes at project level" option is enabled for the RBS, the new resources added at project level are automatically reflected in the RBS.
  • B. If the "Allow resource changes at project level" option is set to No, the new resources and resource formats that are added to a Planning Resource Breakdown Structure for one project are not available for other projects.
  • C. If the "Allow resource changes at project level" option is set to Yes for the RBS, the new resources are available automatically at project level.
  • D. If the "Allow resource changes at project level" option is set to No for the RBS, then the resources added to the Planning Resource Breakdown Structure are automatically available for use on the projects.

Answer: D

Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/fapfm/implementing-project-financial-management-applications.html#FAPFM969761 Topic - Entering Planning Resource Breakdown Structure Details Click Navigator > Setup and Maintenance, and search for the Manage Planning and Billing Resource Breakdown Structures task.
Click the Manage Planning and Billing Resource Breakdown Structures link.
Use the Manage Planning and Billing Resource Breakdown Structures page to create new planning resource breakdown structures and to review existing planning and billing resource breakdown structures.
Click the Create icon in the Planning Resource Breakdown Structures section.
Use the Create Planning Resource Breakdown Structure: Basic Information page to provide basic resource breakdown structure information including the name, active dates, and project unit.
Enter a planning resource breakdown structure name and select a date from which the resource breakdown structure is available for use.
Optionally, provide a description and a date to which the planning resource breakdown structure is available for use.
Select a project unit. Only projects created for the selected project unit can use this planning resource breakdown structure.
If you want to allow project managers to add planning resources at the project level, then select the Allow resource changes at project level check box.
Tip: Changes at the project level don,t move back to the parent planning resource breakdown structure. Deselect this option to ensure all project using the planning resource breakdown structure use the same resources.
Optionally, select a Job Set as a source of jobs for creating planning resources on your planning resource breakdown structure.
Click Save.


NEW QUESTION # 52
Your organization has created an Enterprise Project Structure (EPS) and your executives review the overall project labor demand by using the EPS. Identify two correct statements about the periodic project labor demand.

  • A. Labor Demand FTE is calculated as Quarterly Allocation hours divided by Quarterly FTE hours, if a quarter is used as the basis for viewing labor demand.
  • B. Labor Demand FTE is calculated as Yearly Allocation hours divided by Yearly FTE hours, if a year is used as the basis for viewing labor demand.
  • C. Labor Demand FTE is calculated as Monthly Allocation hours divided by Monthly FTE hours, if a period is used as the basis for viewing labor demand.
  • D. Labor Demand FTE is calculated as Project Allocation hours divided by Project FTE hours, if project duration is used as the basis for viewing labor demand.

Answer: A

Explanation:
Reference https://docs.oracle.com/cloud/farel10/projectcs_gs/OAPEM/OAPEM1461017.htm#OAPEM1313472 Project Labor Demand: How It,s Calculated Project executives want to track the labor demand in projects in their organization. The Project Hierarchy Viewer provides project executives a hierarchical view of the enterprise project structure (EPS) along with the labor demand in terms of full-time equivalent (FTE).
Settings That Affect Project Labor Demand
Project application administrators must do the following to set up how project labor demand is calculated:
Organize projects into hierarchical groups on the Manage Enterprise Project Structure page.
Change the quarterly FTE hours for the organization on the Define Project Management Implementation Options page, if different from 520 hours.
Note: You can choose to view labor demand annually instead of quarterly. The Project Hierarchy Viewer uses the current date to determine which year or quarter to display.
How Project Labor Demand Is Calculated
The Project Hierarchy Viewer calculates project labor demand in the following manner:
Spreads the allocation hours from the Manage Project Resources page evenly over the days that the resources are allocated to the project.
Divides the quarterly project allocation hours by the quarterly FTE hours to get the labor demand.
Rolls up the quarterly and annual labor demand up the hierarchy.


NEW QUESTION # 53
Your customer has implemented Oracle Project Portfolio Management Cloud recently and they have hired new employees for their Professions Services business. These employees are set up in Oracle Human Capital Management Cloud, but the Project Administrators are unable to add them as resources in the Planning Resource Breakdown Structure.
What are three conditions for new employees to show up in the list? (Choose three.)

  • A. All new employees created as persons must have an active assignment.
  • B. All new employees created as persons must have an active project role.
  • C. All new employees created as persons must have an active supervisor.
  • D. Current date is before the effective date of the resource, and you did not enable the "Include people with future-dated effective start dates" option during the search.
  • E. All new employees created as persons must be assigned to a department.

Answer: D

Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/project-foundation-configuration-define-project-resource-breakdown-structures.html#OAPFM180158_2 Why can,t I find persons in the list of resources when I enter team members, planning resources, or person rate schedules?
You can,t find persons in the list of resources when you enter team members, planning resources, or person rate schedules in the following situations:
The administrator didn,t assign a department while creating users. Persons must have an active assignment and be assigned to a department in Oracle Fusion Human Capital Management before they can be added as team members or entered as resources on the planning resource breakdown structure or person rate schedule.
The resource isn,t active in Oracle Fusion Human Capital Management because the current date is before the effective date of the resource. If you want to include persons who will start in the future, select the Include people with future-dated effective start dates option when you search for the person.
Persons assigned as project managers aren,t active as of the project start date.
The assignment of the person is terminated, and an appropriate value isn,t set for the number of days to display people with terminated assignments. You can set the profile value appropriately at the site profile level using the Specify Number of Days to Display People with Terminated Assignments task in the Setup and Maintenance work area.


NEW QUESTION # 54
You have defined two expenditure types but they are not available for selection when you enter an expenditure batch.
What is the reason for this problem?

  • A. The two expenditure types are not assigned to the reference data set that is assigned to the project unit in which the transaction is performed.
  • B. The two expenditure types are not assigned to the reference data set that is assigned to the project expenditure organization in which the transaction is performed.
  • C. The two expenditure types are not assigned to the reference data set that is assigned to the project-owning organization in which the transaction is performed.
  • D. The two expenditure types are not assigned to the reference data set that is assigned to the business unit in which the transaction is performed.

Answer: B

Explanation:
The reason for this problem is that the two expenditure types are not assigned to the reference data set that is assigned to the project unit in which the transaction is performed. Expenditure types are a type of reference data that can be shared across different business units or organizations using reference data sets. To make an expenditure type available for selection when you enter an expenditure batch, you need to assign it to the reference data set that is assigned to the project unit of the transaction. The project unit determines the reference data set for expenditure types. The reference data sets that are assigned to the project expenditure organization, the business unit, or the project-owning organization do not determine the reference data set for expenditure types. These reference data sets may determine other types of reference data such as expenditure categories, expenditure item dates, etc. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-costs.html#OAPFM2356231


NEW QUESTION # 55
Your customer complains that their project resources do not report their time promptly, which has resulted in incorrect reporting of project performance. What should you do to fix this problem? (Choose the best answer.)

  • A. Enable track missing time at business unit.
  • B. Enable track missing time at project type.
  • C. Enable track missing time at project template.
  • D. Enable track missing time at project unit.

Answer: D

Explanation:
To fix the problem of project resources not reporting their time promptly, you should enable track missing time at project unit. This option allows you to track and report on missing time entries for project resources based on their work assignments and schedules. You can also set up notifications and reminders to prompt resources to enter their time on a regular basis. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-time-and-labor.html#OAPFM2356011


NEW QUESTION # 56
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)

  • A. Event completion flows from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
  • B. Project plans and progress flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
  • C. Summarized actual quantity and cost flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.
  • D. Billing events flow from Primavera P6 Enterprise Project Portfolio Management to Oracle Project Portfolio Management Cloud.
  • E. Projects and task definitions flow from Oracle Project Portfolio Management Cloud to Primavera P6 Enterprise Project Portfolio Management.

Answer: A

Explanation:
Ref: https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125394AN6D254.htm Primavera P6 Enterprise Project Portfolio Management and Oracle Fusion Project Portfolio Management: How They Work Together Use Oracle Fusion Project Integration Gateway to integrate Oracle Fusion Project Portfolio Management with Primavera P6 Enterprise Project Portfolio Management. The integration enables project accountants, project billing specialists, and executives to centrally perform project costing, billing, accounting, and executive reporting tasks in Oracle Fusion Project Portfolio Management while enabling each project manager to perform detailed project planning and scheduling in Primavera P6 Enterprise Project Portfolio Management.
Oracle Fusion Project Integration Gateway ensures data security, integrity, and efficiency by defining a set framework in which data is exported from and imported into Oracle Fusion Project Portfolio Management.
The following table and diagram provide an overview of the flow of information.
Information Type
From Application
To Application
Global integration information
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Projects and task definition
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Summarized project actual quantity and cost
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Project plans and progress
Primavera P6 Enterprise Project Portfolio Management
Oracle Fusion Project Portfolio Management
Billing events
Oracle Fusion Project Portfolio Management
Primavera P6 Enterprise Project Portfolio Management
Event completion
Primavera P6 Enterprise Project Portfolio Management
Oracle Fusion Project Portfolio Management


NEW QUESTION # 57
You want to create a few project roles so as to restrict access in the Project Financial Management work area to only the specific projects in which an employee is assigned as a team member. What are the two default project roles available to meet this requirement?

  • A. Project Manager - Security based on Project Assignment
  • B. Project Team Member - Security based on Project Assignment
  • C. Project Billing Specialist - Security based on Contract BU
  • D. Project Accountant - Security based on BU for Assets, Expenditure BU for Costs and Contract BU for Revenue
  • E. Project Executive - Security based on Project Hierarchy

Answer: A

Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/applications-common/r13-update17d/faser/implementing-security-in-oracle-fusion-project-portfolio-management.html#FASER1840867


NEW QUESTION # 58
You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)

  • A. S
  • B. R
  • C. P
  • D. Q

Answer: C

Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapem/evaluate-and-assign-resources.html#OAPEM916359 Topic - Resource Available Capacity Score: How It,s Calculated Calendars Used to Calculate Resource Available Capacity Scores How the Resource Available Capacity Score Is Calculated


NEW QUESTION # 59
Your organization has a requirement to retrieve the value of the cost center segment based on the department.
Which source can you use while defining the account rule to achieve this requirement?

  • A. Expenditure Business Unit Cost Center Segment
  • B. Project Organization Cost Center Segment
  • C. Expenditure Organization Cost Center Segment
  • D. Event Organization Cost Center Segment

Answer: C

Explanation:
The source that can be used while defining the account rule to achieve this requirement is Expenditure Organization Cost Center Segment. This source allows you to retrieve the value of the cost center segment based on the expenditure organization of the transaction. The expenditure organization is an attribute of a transaction that represents the organization that incurs or owns the cost of the transaction.


NEW QUESTION # 60
While opening an organization tree on the Manage Organization Trees page, you notice that the hierarchy status is displayed as Inactive. Identify the two reasons for the organization tree to be in Inactive status.

  • A. You opened the hierarchy by clicking the name.
  • B. You used Create Tree Version in the action menu.
  • C. You used View Tree Version in the action menu.
  • D. You selected the Edit icon for opening the hierarchy.
  • E. You used Create Tree in the action menu.

Answer: A

Explanation:
When you use Create Tree or Create Tree Version in the action menu, you create a new organization tree or a new version of an existing tree, respectively. These actions result in an Inactive status for the organization tree, until you activate it. When you use View Tree Version or select the Edit icon or click the name of the tree, you open an existing organization tree that has an Active status. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-organizations.html#OAPFM2355921


NEW QUESTION # 61
Your organization has decided to enable the common accounting and project accounting periods option while defining business unit implementation options.
Where will you maintain the accounting period statuses if this option has been enabled?

  • A. Project Foundation
  • B. Project Costing
  • C. Subledger Accounting
  • D. General Ledger

Answer: D


NEW QUESTION # 62
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

  • A. Remaining Plan
  • B. Manual Entry
  • C. Effort
  • D. Cost

Answer: C

Explanation:
Reference https://ppm-help.saas.hpe.com/en/9.42/Help/Content/UG/PjMUG/view_pj_cost_data_costtab.htm Below is an example of the Financial Summary view on the Cost tab of the Project Overview page.


NEW QUESTION # 63
You have a billable project for which the following details are provided:
Associated Inception-To-Date (ITD) Project Actual Cost: USD 60
Associated Project Budgeted Cost: USD 300
Contract Amount: USD 1000
Project Funded Amount: USD 750
Sum of Existing Revenue Events: USD 80
Identify the Associated Project Spent revenue that will get generated based on the preceding details. (Choose the best answer.)

  • A. USD 184
  • B. USD 70
  • C. USD 134
  • D. USD 120

Answer: D

Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjb/manage-project-contract-revenue.html#OAPJB164173 Associated Project Percent Spent Example The following formula calculates the percent spent revenue for the associated project.
((Sum of ITD Actual Cost for every subtask that is part of the associated task / Sum of Total Budgeted cost for every task that is part of associated task) x Associated Project Funded Amount) - Sum of Existing Invoice Event Amounts for the Associated Project ((60/300) x 750) - 80 = 70 ((Actual Cost / Budgeted Cost) x Budgeted Revenue) - Sum of Revenue Event Amount


NEW QUESTION # 64
Which three tasks can be performed using the project requirements work area? (Choose three.)

  • A. adding scrum master to backlog items.
  • B. tracking backlog item status from the requirement storyboard.
  • C. creating change orders for the backlog items.
  • D. creating projects and tasks in the context of backlog items.
  • E. creating issues for the backlog items.

Answer: D

Explanation:
The project requirements work area is a work area that allows you to define and manage requirements for your projects using various methods and sources. Requirements are statements of needs or expectations that must be met by the project outcome. Backlog items are a type of requirement that are used for agile projects that follow an iterative and incremental approach. Three of the tasks that can be performed using the project requirements work area are:
creating projects and tasks in the context of backlog items: This task allows you to create new projects and tasks or link existing projects and tasks to backlog items. This helps you to plan and execute the work that is required to fulfill the backlog items.
creating issues for the backlog items: This task allows you to create new issues or link existing issues to backlog items. Issues are problems or risks that affect the progress or outcome of a project or requirement. This helps you to track and resolve the issues that are related to the backlog items.
tracking backlog item status from the requirement storyboard: This task allows you to view and update the status of backlog items from the requirement storyboard. The requirement storyboard is a graphical representation of the progress and completion of backlog items using various stages and lanes. This helps you to monitor and control the delivery of backlog items. Adding scrum master to backlog items and creating change orders for the backlog items are not tasks that can be performed using the project requirements work area. Adding scrum master to backlog items is a task that can be performed using the project team work area, as scrum master is a role that is assigned to a project team member who facilitates and coordinates the agile project activities. Creating change orders for the backlog items is a task that can be performed using the project change management work area, as change orders are documents that capture and approve changes to a project scope, schedule, or budget. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-execution.html#OAPFM2356321


NEW QUESTION # 65
After completing setups in a source environment, your customer wants to move the setup data to a target environment. Identify the two statements related to task list scope, which you must consider before taking a decision based on the customer requirement.

  • A. A task list can be segmented by a scope value and a task can be performed for each qualifying value of the selected object.
  • B. Exported setup data cannot be filtered by specific scope values if the business object has scope enabled for the setup data export.
  • C. A scope value is used to assign users who can perform a task within an implementation project.
  • D. Exported setup data can be filtered by specific scope values if the business object has scope enabled for the setup data export.

Answer: C

Explanation:
Reference https://docs.oracle.com/cd/E60665_01/common/OAFSM/OAFSM1166430.htm#OAFSM1166426


NEW QUESTION # 66
You are implementing Project Portfolio Management (PPM) for a professional services firm. The firm rents multiple buildings for its operations. At the end of each month, they review the rent expense for the month and want to allocate the rental cost to all the projects and tasks that are executed by associates in each of the buildings. The source amounts must be proportionally allocated to the tasks based on the raw costs of the tasks from the previous month. Considering that all these costs are in General Ledger, what three allocation setups should you complete in PPM? (Choose three.)

  • A. Allocate rental costs once each accounting period by using the "spread evenly" allocation method.
  • B. Allocate to all eligible tasks and prorate the allocation by the total actual raw cost accrued for each task during the previous accounting period.
  • C. Define allocation basis by using Actual Amounts with a project-to-date amount class.
  • D. Define allocation basis by using Actual Amounts with a period-to-date amount class.
  • E. Allocate rental costs once each accounting period by using the "full" allocation method.

Answer: E

Explanation:
To allocate the rental cost to the projects and tasks based on the raw costs of the tasks from the previous month, you need to do the following:
Allocate rental costs once each accounting period by using the "full" allocation method. This method allocates the entire source amount to the target tasks in one run.
Allocate to all eligible tasks and prorate the allocation by the total actual raw cost accrued for each task during the previous accounting period. This ensures that the source amount is proportionally allocated to the tasks based on their relative raw costs.
Define allocation basis by using Actual Amounts with a period-to-date amount class. This allows you to use the actual raw costs of the tasks as the basis for allocation and to use the amounts from the previous accounting period. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/manage-project-costs.html#OAPFM2355951


NEW QUESTION # 67
You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contract Line 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X - Task 10, and Bill Plan B is allocated against Project Y - Task 30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario.

  • A. Both the contract lines create only a single invoice because they are using the same contract.
  • B. Two invoices are created using the same contract.
  • C. Bill set number drives the grouping of transactions.
  • D. Invoice generation does not depend on bill plan. The invoices are created based on the contract line.

Answer: A

Explanation:
Ref: https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJB/F1087456AN1006D.htm What,s a bill set?
Transactions originating from different bill plans with the same bill set number on a contract are included on the same invoice. If a contract has multiple bill plans and each have different values for the bill set, Oracle Fusion Project Billing creates a separate invoice for each bill plan


NEW QUESTION # 68
You want to export your project plan to Oracle Project Financial Management Cloud after initial scheduling is complete in Microsoft Projects.
Identify three conditions that must be met for exporting milestone tasks.
(Choose three.)
Response:

  • A. lowest-level tasks set up with non-zero duration
  • B. only one labor resource assignment with 100 effort
  • C. only one labor resource assignment with 0 effort
  • D. percent work complete values of 0 or 100 percent
  • E. lowest-level tasks set up with zero duration

Answer: B,C,D


NEW QUESTION # 69
Which data format is supported by SOAP Web services to establish communication between web services consumers and web services providers?

  • A. XLSX
  • B. CSV
  • C. JSON
  • D. XML

Answer: D

Explanation:
XML (Extensible Markup Language) is the data format that is supported by SOAP (Simple Object Access Protocol) Web services to establish communication between web services consumers and web services providers. XML is a standard format that allows data to be exchanged across different platforms and applications. SOAP Web services use XML to encode the messages and data that are sent and received between the web services endpoints. https://docs.oracle.com/en/cloud/saas/project-portfolio-management/20c/oapfm/integrate-project-financial-management.html#OAPFM2356071


NEW QUESTION # 70
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)

  • A. Expenditure Type
  • B. Contract Header
  • C. Projects
  • D. Contract Line
  • E. Task

Answer: A

Explanation:
Reference https://docs.oracle.com/cloud/farel9/projectcs_gs/FAUAR/F1537947AN10251.htm